Church Building Project
01-19 December 2006

Click each image for a larger version.
01-Dec-06
Ceiling framing in main nave started.
01-Dec-06
Ceiling framing in main nave started.
05-Dec-06
More ceiling framing in main nave.
19-Dec-06
Ceiling to main nave being installed. Note the ceiling insulation. (There is anti-con.insulation directly under the roof sheeting too!)
19-Dec-06
Pulpit bricked up and ceiling installed over. Pulpit will be faced with "Donnybrook Stone" on the exterior vertical faces.

photos by Harry Hordyk.